The construction of Interior and Exterior Works for New PPCBank_Koh Kong Province (Zhe Jaing SEZ) Branch

Published Date: March 28, 2025

1, Requirement

Participant in the construction of Interior and Exterior works for New of PPCBank_Koh Kong (Zhe Jaing SEZ) Branch

Expected Construction Period: From 21st April 2025 to 9th Jun 2025 (Max 1.5 months)


Note:

The construction period can be extended depending on unexpected circumstance on mutual consents with PPCBank.

2, Field descriptions

Reference to the Layout contents with the following details

  • Interior works

    Ground Floor

    1. Deposit Counter (3 tellers, 1 chief teller)

    2. Loan office (4 loan officers, 1 chief loan officer)

    3. Vault Room (at least 16 m)

    4. 3 Meeting rooms for deposit customers

    5. Pantry room including sink

    6. Server room

    7. Electrical room

    8. Storage rooms (file)

    9. Toilet (WC) (proper size for the number of working staff)

  • Note for interior design

    • All mentioned above or more, participant in the construction of in-exterior shall suggest design at your discretion and by efficiently arranging it in the layout and please refer to current branch design and layout etc.

    • Counters face to the entrance door.

    • Submission 3D design at your discretion and suggestion to improve branding.

    • Quotation including M&E (Reference to specification of Layout) shall be submitted.

    • Quotation of network and telephone shall be submitted separately by attaching company profile including specific network and telephone, vendor name and contact information.

  • Exterior works

    1. ATM Booth (2 ATMs)

    2. Signboard (arrangement is required considering the electric line, it does not have to be the same as the existing signboard created suggestions are required)

    3. Toilet (WC) for security guards

    4. Parking lot in front the building

  • Note for Exterior design

    • Submission 3D design at your discretion based on any suggestion to improve branding image.

    • Note: Please refer to PPCBank design of current branches design.

3, Submission deadline for applications

Tuesday, 8th April 2025 (11:00 AM)

4, How to submit your application
  • Application documents shall be submitted to Administrative Department of PPCBank.

  • PPCBank HQ Building Address: Nº 217, Norodom Blvd., Phum 10, Sangkat Tonle Bassac, Khan Chamkarmorn, Phnom Penh, Cambodia

Application documents shall be enclosed with the company seal.

5, Application Documents

Company introduction including such as company name, establishment year, capital, total assets, previous year’s net profit, number of employees, major business field, representative nationality

6, Applicant qualification

Company related to the construction of interior and exterior that registered business in Cambodia.

7, Decision-making method of company

Decision is according to the bank’s internal regulations.

8, Application Deposit

None

9, Result notification date

PPCBank will notify on proper date before construction.

10, Signing of contract for construction

Within 10 days from the date of notification of the result

11, What to note when submitting your application
  • Identify guidelines, regulations, special conditions, etc. of local authority in relation to facility

  • Inspection procedure will be carried out after completion of construction

If you have any concern, please feel free to contact us.

Mr. YUN Chang Ho, Senior Manager (Korean)/ Tel: 012 850 513

Mr. PHAN Sovanndos, Administrative Manager (Khmer)/ Tel: 089 669 967